1. Crushing system configuration
Two-stage crushing process
Primary crushing: PE250×400 jaw crusher (feed size ≤210mm, discharge size ≤60mm)
Secondary crushing: PGY800×600 roller crusher (discharge size ≤15mm)
Supporting equipment: GZD650×2300 vibrating feeder + TD75 belt conveyor system
Key technical parameters
Processing capacity: 3-5t/h (adjustable)
Power configuration: total installed capacity ≤45kW
Dust removal system: pulse bag dust collector (handling air volume 3000m³/h)

2. Flotation system design
Core equipment selection
Flotation machine: XJK-0.35 mechanical stirring flotation machine (4 tanks in series)
Reagent preparation: YJB-500 reagent mixing barrel (with metering pump)
Dehydration equipment: GNZ-3 high-efficiency concentrator + 750×750 plate and frame filter press

Process flow
Grinding (-200 mesh accounts for 65%) → Roughing (butyl xanthate 60g/t) → Scavenging (2 times) → Concentration (3 times)
→ Concentration and dehydration (final copper concentrate water content ≤18%)
Operation indicators
Ore grade: 0.8-1.2%Cu
Concentrate grade: ≥18%Cu
Recovery rate: 85-90%
Power consumption: ≤35kWh/t

3. Environmental protection and safety measures
Fully enclosed design of crushing workshop + sound insulation cotton (noise ≤75dB)
Tailings water circulation system (reuse rate ≥85%)
Flotation reagent automatic filling system (error ±2%)
Technical Analysis of Structure and Application of Mineral Slag Mixing Tank
2026.10.131500×4500 Ball Mill: Specifications, Advantages, and Availability
2026.10.09Green development has become the new guiding direction for the ball mill equipment industry
2026.09.29Comparison and Selection of Jaw Crusher and Impact Crusher for Mineral Processing Equipment
2026.09.22